A. Submission of Project Permit Application and Associated Concurrency Application. Every project permit application must be accompanied by a concurrency application (under Chapter 19.10 GHMC), unless the development described in the application is exempt under Article I of Chapter 19.10 GHMC. The planning department shall immediately forward the concurrency application to the public works/engineering department for processing. The planning department shall then determine whether or not the project permit application is complete, following the procedures in this section.

B. The public works/engineering department shall notify the planning department within 28 days after initial receipt of the applications whether the concurrency application is complete or incomplete. The planning department shall not make a finding that the project permit application is complete under this section unless and until notified by the public works/engineering department that the concurrency application is complete.

C. Determination of Completeness. Within 28 days after receiving a project permit application, the city shall mail or personally deliver to the applicant a determination which states either:

1. That the application is complete; or

2. That the application is incomplete and what is necessary to make the application complete.

If an applicant chooses the optional consolidated permit review process set forth in GHMC 19.01.002(B), the determination of completeness shall include all project permits being reviewed through the consolidated permit review process.

D. Identification of Other Agencies with Jurisdiction. To the extent known by the city, other agencies with jurisdiction over the project shall be identified in the determination of completeness.

E. Additional Information. A project permit application is complete for the purposes of this section when it meets the submission requirements of GHMC 19.02.002, the submission requirements of the applicable development regulations, and when the public works/engineering department has determined that a complete concurrency application has been submitted. The determination of completeness shall be made when the application is sufficiently complete for review, even though additional information may be required or project modifications may be undertaken subsequently. The director’s determination of completeness shall not preclude the director’s ability to request additional information or studies whenever new information is required, or substantial changes are made to the proposed project.

F. Incomplete Applications.

1. Whenever the applicant receives a determination from the city that an application is not complete for either a project permit or concurrency application, the applicant shall have 90 days to submit the necessary information. Within 14 days after an applicant has submitted the requested additional information, the director shall make a determination of completeness and notify the applicant in the manner provided in subsection C of this section.

2. If the applicant does not submit the additional information requested within the 90-day period, for either the project permit or concurrency application, the director shall make findings and issue a decision, according to the Type I procedure described in GHMC 19.01.003, that the application has lapsed for lack of information necessary to complete the review. The decision shall state that no further action will be taken on the applications, and that if the applicant does not make arrangements to pick up the application materials from the planning and/or public works/engineering departments within 30 days from the date of the decision, the application materials will be destroyed.

3. When the director determines that an application has lapsed because the applicant has failed to submit required information within the necessary time period, the applicant may request a refund of the application fee remaining after the city’s determination of completeness.

G. Director’s Failure to Provide Determination of Completeness. A project permit application shall be deemed complete under this section if the director does not provide a written determination to the applicant that the application is incomplete as provided in subsection C of this section. This subsection G shall not apply to a concurrency application.

H. Date of Acceptance of Application. Project permit and concurrency applications shall not be officially accepted until complete. When an application is found complete, the director shall note the date of acceptance for continued processing. (Ord. 1197 § 93, 2010; Ord. 1043 § 1, 2006; Ord. 806 § 9, 1998; Ord. 711 § 1, 1996).