A. The city shall charge the following general facilities charge to connect to the water utility system:

Meter Size

Capacity Factor

General Facilities Charge

3/4"

1.0

$7,300.00

1"

1.67

12,191.00

1-1/2"

3.33

24,309.00

2"

5.33

38,909.00

Over 2"

Per AWWA Formula

Per City Formula

B. Any remodel and/or use change shall pay the difference between the new use and/or size and the previous use and/or size. No refund shall be allowed for use and/or size reduction.

C. Water system general facility charge for connections outside the city limits shall be charged at one and one-half times the city rates.

D. Each general facilities charge shall be paid to the city at the time of building permit issuance. Where capacity is increased as outlined in Chapter 19.10 GHMC but no building permit is required, each general facilities charge shall be paid at the time capacity is increased. (Ord. 1319 § 5, 2015).