All new water service connections and all water service connections and all water service which is re-installed or reconnected after disconnection shall be subject to the requirements:

A. Tap Size Determination. The superintendent may determine the size of tap to be inserted into any water main and the size of service pipe under any application or permit, provided that no service shall be less than three-quarters inch in diameter.

B. 

1. Pipe Installation. When a permit has been obtained for the installation of water, the superintendent, if there is a city water main abutting the property, shall cause to be installed a service pipe from the main to the property line, including a stopcock, meter and meter box, which connections thereafter shall be maintained by and kept within the exclusive control of the city.

2. The council may, at its discretion, order the extension or renewal of mains by the use of local improvement districts or utility local improvement districts as provided by law, and the water department may pay the same, whatever part is deemed equitable, as determined by the council. (Ord. 369 § 5, 1981).