A. No applicant may make a change to an approved base plan, except the city may require changes in the plan if an error is detected.

B. Any change to a base plan found during inspection will void the building permit issued for use of the base plan. If the permit is voided under this subsection, the holder of the permit shall re-apply for a new building permit, paying the building permit application fees for new construction. The applicant will be credited with 80 percent of the original permit fee. A new plan review fee as set forth in a resolution adopted by the council for this purpose shall be paid and the base plan review fee will not be refunded.

C. A stop work order shall issue for any base plan project changed in accordance with subsection B of this section. Construction shall not be allowed to continue until after issuance of a new building permit for the project. (Ord. 1387 § 1, 2018; Ord. 1041 § 1, 2006).