A. Path A – Base Plan Application for New Plans. A complete application for a base plan shall consist of all of the following:

1. Completed base plan application specifying that the plans are submitted for the establishment of a base plan;

2. When applicable, written permission from the engineer and/or architect of record approving repetitive use of the design;

3. Complete structural and architectural plans including foundation, floor, and framing plans, details, structural sections, building elevations, and any proposed options, using an electronic format approved by the building and fire safety division;

4. Complete code notes including specification of the code (IBC/IRC) and edition under which the design was completed;

5. Any other information deemed by the building official/fire marshal to be necessary to demonstrate code compliance.

B. Path B – Base Plan Application with Site-Specific Component.

1. Completed base plan application specifying that the plans are submitted for the establishment of a base plan and a complete building permit application as prescribed under GHMC 15.08.020 for use of the base plan when established;

2. When applicable, written permission from the engineer and/or architect of record approving repetitive use of the design;

3. Complete structural and architectural plans including foundation, floor, and framing plans and details, structural sections, building elevations, and any proposed options, using an electronic format approved by the building and fire safety division;

4. Complete code notes including specification of the code (IBC/IRC) and edition under which the design was completed;

5. Any other information deemed by the building official/fire marshal to be necessary to demonstrate code compliance.

C. Path C – Base Plan Application for Previously Reviewed Plans. A complete application to establish a base plan from previously approved plans shall consist of the following:

1. Completed construction application specifying that the plans are submitted for the establishment of a base plan;

2. When applicable, written permission from the engineer and/or architect of record approving repetitive use of the design;

3. Complete structural and architectural plans including foundation, floor, and framing plans and details, structural sections, building elevations, and any proposed options bearing the city approval stamp, using an electronic format approved by the building and fire safety division;

4. Complete code notes including specification of the code (IBC/IRC) and edition under which the design was completed;

5. Any other information deemed by the building official/fire marshal to be necessary to demonstrate code compliance;

6. If a site-specific construction component is included, a complete building permit application as prescribed under GHMC 15.08.020 for use of the base plan when established.

D. Application for a Building Permit from a Previously Established Base Plan. A complete application for a building permit for use of an existing base plan shall consist of:

1. Complete building permit application as provided under GHMC 15.08.020.

2. Complete plan sets identical to those in the base plan on file. Approved options used shall be clearly identified on the plans, with unused options struck through, using an electronic format approved by the building and fire safety division.

3. When the applicant is other than the base plan holder of record, written permission from the base plan holder for the use of the base plan. (Ord. 1387 § 1, 2018; Ord. 1041 § 1, 2006).