A. The applicant shall develop a wetland mitigation plan that provides for construction, maintenance, monitoring and contingencies of the replacement wetland. In addition, the applicant and landowner shall meet the following criteria:

1. The restored, created, or enhanced wetland shall be as persistent as the wetland it replaces;

2. The applicant shall demonstrate sufficient capability to carry out the compensation project;

3. The compensation area shall be provided with permanent protection and management to avoid further development or degradation and to provide for the long-term persistence of the compensation area as designed.

B. In cases in which it is determined that compensatory mitigation is appropriate, the following shall apply:

1. Compensatory mitigation shall be provided on-site, except where on-site mitigation is not scientifically feasible or practical due to physical features of the site. The burden of proof shall be on the applicant to demonstrate that mitigation cannot be provided on-site.

2. When compensatory mitigation cannot be provided on-site, mitigation shall be provided in the immediate vicinity of and within the same watershed as the permitted activity.

3. Compensatory mitigation shall duplicate the overall functions and values of the wetland to be replaced and shall include at least 50 percent in-kind compensation mitigation unless it can be demonstrated by the applicant that the overall wetland values of the mitigation area and adjacent or connecting wetlands can be enhanced by a higher percentage of out-of-kind mitigation.

4. Only when it is determined by the department that subsections (B)(1), (2) and (3) of this section are inappropriate and/or impractical shall off-site, compensatory mitigation be considered.

5. Mitigation projects shall be completed concurrent with other activities on the site, unless a phased schedule is agreed upon between the department and the applicant. Refer to GHMC 18.08.170 for guidelines on determining wetland acreage replacement ratios. (Ord. 1036 § 23, 2006; Ord. 611 § 1, 1991).